The proposed development lies approximately 18km north-west of Perth within the land of Scone Estates, comprising 13 turbines with a mixture of 180m and 200m maximum tip heights. 

The project is a continuation of Scone Estates undertaking a holistic approach to its estate management, with tackling the climate emergency and addressing nature crisis as key elements.

Following three years of surveys and assessments, and substantial consultation with local community and other key stakeholders, the Section 36 Application and associated Environmental Impact Assessment has now been submitted to the Scottish Government Energy Consents Unit.

All of the documents submitted to the Energy Consents Unit in support of this proposal are available for viewing and download at the link below or at www.energyconsents.scot under ECU reference  ECU00006004.  

The Non Technical Summary provides a helpful overview of what is contained in the detailed documents.

Printed copies of all documents will be made available to view in person at Bankfoot Church Centre, Birnam Arts and Chapelhill Hall during normal opening hours. 

View the statutory notice, including details of how to formally share your views on the application, below:

North Logiealmond Wind Farm Planning Application

Supporting Documents

Following community feedback, we developed a new interactive visualisation tool that allows the viewer to compare the initial and final submission layouts from a selection of local viewpoints and to explore the habitat enhancement planned and the reduced aviation lighting proposals.

An interactive version of the Design and Access Statement is also available.

These tools can be explored below.

NEW interactive visualisation tool

Explore

NEW Interactive Design & Access Statement

Explore

Submit a representation to Energy Consents Unit

Submit

If you support the North Logiealmond proposal

Let Us Know

View our Socio Economic brochure

turbine icon

13

Turbines

height icon

180 & 200 m

Maximum Tip Heights

generating icon

93.6MW

Generating Capacity

carbon icon

118,897

Tonnes of CO2 saved each year

supplies icon

86,576

Homes Powered

Location: Perth and Kinross

April 2023

Ecological and Ornithological surveys commence

October 2024

Submission of Scoping application to Energy Consents Unit

November 2024

First community consultation events with local communities

Early 2025

Engagement with statutory and non-statutory consultees following scoping submission.

May 2025

Second Round of Community Consultation Events.

Autumn 2025

Ongoing stakeholder and public engagement, design and assessment work

Winter 2025/26

Finalise proposals and update communities

Summer 2026

Submission of Section 36 Application. Public representations welcomed by Scottish Government Energy Consents Unit

2026 2027

Ongoing determination of application

With the proposed 13 turbine development, our community investment commitment of £7,000 per MW of installed capacity would provide the community with more than £655,000 of funding every year. 

Andrew Marshall, Senior Project Manager

Community Involvement

Muirhall Energy is committed to the principles of community wealth building and a just transition to a net-zero economy and we engage with communities from the earliest stages of a project.

The North Logiealmond project presents an opportunity to investigate how investment can be shared in an innovative and equitable way with communities who would not typically benefit from wind farm development, including deprived urban areas. 

Muirhall will continue to work closely with the Host Communities to ensure the effective implementation of any community investment package

Public Engagement & Project Documents

Muirhall Energy held two rounds of public consultation events in November 2024 and May 2025.


In early 2026, we held a series of information events across consecutive weeks in Bankfoot, Chapelhill and Birnam. These events presented information on the final design of the wind farm, which will be submitted for planning, and how the feedback received to date has shaped these proposals.

Information presented at the latest events, and the community newsletter inviting residents to attend, are available via the links below.

Interested in partnering with Muirhall Energy?

Local businesses close to our renewable energy developments can be added to our supply chain register, ensuring that their interest in working on our projects will be highlighted to the appropriate contacts within Muirhall Energy and to our main contractors.  Learn more and register here.

Get in touch

For any queries relating to our proposed North Logiealmond development, please do not hesitate to get in touch by emailing northlogiealmondwf@muirhallenergy.co.uk